Milton District Hospital Expansion Timeline

2011



Community

With government approval of the expansion received in 2011, the planning process began immediately.

2012

 

December 2012

Community

Functional Program submitted

The Functional Program for the expansion was developed to provide detailed descriptions of the services that will be offered and the resources required to support them. This important document, which was submitted to the Ministry of Health and Long-Term Care for approval, also provided instruction for the architectural and engineering team for the preparation of preliminary building designs.

2013

During this time Halton Healthcare worked to develop output specification documents which formed the guidelines and performance requirements within which the successful building team were required to work when preparing their overall design proposals.

September 2013

Community

September 4, 2013 - Sign Unveiling

Request for Qualifications issued

The RFQ was the first step in the process to select a team to design, build, finance and maintain the new facility.  During this period three teams were pre‚Äźqualified to proceed to respond to the request for proposals.

January 2015

Preferred Proponent selected

Following an open, fair and competitive request for proposal process, Plenary Health was announced as the preferred proponent selected to design, build, finance and maintain the expansion at Milton District Hospital.

March 2015

Contract awarded

Following comprehensive negotiations with the preferred proponent a fixed price contract was awarded to Plenary Health to design, build, finance and maintain the Milton District Hospital expansion project.

March  2016



Sign

Official Groundbreaking

It was a groundbreaking affair when Halton Healthcare staff, physicians, volunteers, local officials, and Milton residents, joined by special guest the Honorable Dr. Eric Hoskins, gathered on the grounds of Milton District Hospital to officially kick off construction.

June 2016



Sign

Topping off Ceremony

On Friday, June 3, 2016, the Honourable Eric Hoskins, Minister of Health and Long-Term Care and Indira Naidoo-Harris, MPP Halton, joined representatives from Halton Healthcare, the Town of Milton, the Milton District Hospital Foundation, the Milton District Hospital Auxiliary and numerous members of the construction team to celebrate the official topping off of the Milton District Hospital Expansion. The topping off ceremony is a traditional construction celebration that is held to signify that the highest point of the building has been reached.

 

Spring 2017

keys

Substantial Completion

Halton Healthcare is looking forward to Substantial Completion. This major milestone marks the completion of construction. It is at this time that the hospital will have full access to the building to prepare for the move into the expansion space.

 

Spring - Fall 2017

Facility Activation

Relocating to new facilities with modern design and advanced technologies brings a lot of changes to the way staff, physicians and volunteers work and provide care. During this time staff, physicians and volunteers will be participating in detailed orientation and training to ensure they are ready to provide care to our patients when the expansion opens. Other activities will include installing and testing equipment, testing building systems and extensive cleaning.

Fall 2017

Opening Day Image

Opening Day

A detailed move plan will ensure the departments that are relocating into the new space are prepared for move day. This massive undertaking will involve the teamwork of every department and service.

Uncommon content coming soon.